据今日石油网2022年1月26日报道,圭亚那政府内阁周三向国会提交了2022年国家预算,披露了208亿圭亚那元(圭元)将被指定用于具有里程碑意义的天然气转化能源项目。
由于圭亚那的能源需求预计在未来5年内将增长,圭亚那政府计划通过使用天然气将电力成本降低50%。 这也将有助于逐步淘汰昂贵且碳密集的重燃料油。
这个把天然气转化能源的项目将建设一座发电能力为300兆瓦(MW)的发电厂,以及一座天然气液体(NGL)厂来满足圭亚那的国内电力需求。
此外,圭亚那还将建设一条长225公里的直径12英寸的管道,以“保证最低限度”将5000万标准立方英尺/天的天然气从圭亚那海上输送到Wales开发局。
圭亚那政府负责财政的高级部长Ashni Singh博士详细介绍说,到目前为止,正在进行的海上和陆上地质和地球物理工作正在推进,部分工作已经完成。此外,环境和社会影响评估预计将于今年第二季度初完成。
Singh博士强调,通过透明的采购流程,预计被选中的公司将能够设计、采购和建造发电厂和天然气液体厂以及相关设施。预计今年第三季度开始建设,2024年第四季度建成投产。
李峻 编译自 今日石油网
原文如下:
Guyana government to pump GY$20.8 billion into landmark gas-to-energy project
The Guyana government presented its 2022 National Budget on Wednesday in the National Assembly where it was disclosed that GY$20.8 billion dollars is being earmarked for the landmark gas-to-energy project.
With the country’s energy demand expected to grow within the next five years, the government has eyed the reduction of electricity costs by 50 percent through the use of natural gas. And it will also help to phase out the use of expensive and carbon-intensive heavy fuel oil.
The gas-to-energy project will see a power plant being constructed to generate 300 megawatts (MW) of power and a Natural Gas Liquids (NGL) plant to cover Guyana’s domestic demand.
A 225 km 12” pipeline will also be constructed to transport the “guaranteed minimum” of 50 million standard cubic feet per day (mmcfd) of natural gas from offshore Guyana to the Wales Development Authority.
Senior Minister with responsibility for Finance, Dr. Ashni Singh detailed that thus far, ongoing geotechnical and geophysical works for both offshore and onshore operations are advancing with portions already completed.
And further, an Environmental and Social Impact Assessment is expected to be completed early in the second quarter of 2022.
Dr. Singh highlighted that using a transparent procurement process, it is expected that the firm selected would be able to engineer, procure and construct the Power Plant and NGL Plant along with related facilities.
Construction is expected to start in the third quarter of 2022 and will be completed by the fourth quarter of 2024.
免责声明:本网转载自其它媒体的文章,目的在于弘扬科技创新精神,传递更多科技创新信息,展示国家科技形象,宣传国家科技政策,增强国家科技软实力,参与国际科技舆论竞争,提高国际科技话语权,并不代表本网赞同其观点和对其真实性负责,在此我们谨向原作者和原媒体致以崇高敬意。如果您认为本网文章及图片侵犯了您的版权,请与我们联系,我们将第一时间删除。