   2022-03-09 互联网综合消息
45
核心提示:据钻机地带3月7日消息称,英国石油和天然气公司IOG已经完成了其土星银行项目开发的陆上接收设施的工作。这

据钻机地带3月7日消息称,英国石油和天然气公司IOG已经完成了其土星银行项目开发的陆上接收设施的工作。

这是从英国北海南部气田开采天然气的最后一步。也就是说,IOG表示,土星银行接收设施(SBRF)的所有建设、调试和功能测试活动都已完成,并已全部签署。该公司还证实,英国健康和安全执行局要求的澄清已经解决。

IOG还表示,启动前的安全审查和操作演练已经结束。这使得该公司及其管道和平台运营商ODE Asset Management和Bacton终端运营商Perenco UK完全满意于2021年3月4日开始返输处理。

该公司解释道:“返输是指气体从终端反向流动,将管道系统加压至启动时的安全操作窗口,在开始正向流动之前,对设备和安全系统进行最终功能测试。受天气和物流的影响,反气和开井过程可能需要大约一周的时间,之后IOG将在陆上迅速收到第一份销售天然气。”

IOG首席执行官Andrew Hockey表示:“我很高兴地说,陆上土星银行接收设施(SBRF)现在已经完全投入使用,管道返输工作已于今天开始。”

“这是我们预计在大约一周内获得第一批天然气的最后一步。我要感谢终端运营商 Perenco,他们非常努力地确保陆上设施安全并为 IOG 的首次生产做好准备。”他补充道。

IOG 运营的土星银行项目第一期于2019年10月获得批准。该油田包括英国北海南部的Blythe、Elgood和Southwark油田。IOG持有该项目50%的股份,其合作伙伴CalEnergy Resources持有剩余50%的股份。

朱佳妮 摘译自 钻机地带

原文如下:

IOG North Sea Fields Ready For Start-Up

UK oil and gas firm IOG has completed work on onshore reception facilities for its Saturn Banks project development.

This is the final step to first gas from its Southern North Sea gas fields. Namely, IOG said that all construction, commissioning and function testing activities at the Saturn Banks Reception Facilities (SBRF) were completed and fully signed off. The company also confirmed that the required UK Health and Safety Executive clarifications had been addressed.

IOG also said that the pre-start-up safety review and operations walk-down have been concluded. This enabled the company, its pipeline, and platform operator ODE Asset Management, and Bacton terminal operator Perenco UK to be fully satisfied to begin the backgassing process on March 4, 2021.

“Backgassing involves a reverse flow of gas from the terminal to pressurize the pipeline system up to the safe operating window for start-up, with final function tests of equipment and safety systems before forward flow can begin. Subject to weather and logistics, the backgassing and well start-up sequence is likely to take approximately one week, with first IOG sales gas to be received onshore rapidly thereafter,” the company explained.

“I’m very pleased to say that the onshore Saturn Banks Reception Facilities (SBRF) have now been fully commissioned and pipeline backgassing has started today,” Andrew Hockey, CEO of IOG, stated.

“This is the final step to first gas which we expect in approximately one week. My thanks go to terminal operator Perenco who have worked very hard to ensure the onshore facilities are safe and ready for IOG’s first production,” he added.

The IOG-operated Saturn Banks Project – Phase 1 was sanctioned in October 2019. It consists of Blythe, Elgood, and Southwark fields in the UK Southern North Sea. IOG holds a 50 percent stake in this project and its partner CalEnergy Resources holds the remaining 50 percent.

The project is looking for a gross peak production rate of 140 mmscf/d – 24,000 Boe/d – from gross 2P gas reserves of 302 Bcfe and management estimated 2C gas contingent resources of 132 Bcfe.



免责声明:本网转载自其它媒体的文章,目的在于弘扬科技创新精神,传递更多科技创新信息,宣传国家科技政策,展示国家科技形象,增强国家科技软实力,参与国际科技舆论竞争,提高国际科技话语权,并不代表本网赞同其观点和对其真实性负责,在此我们谨向原作者和原媒体致以崇高敬意。如果您认为本网文章及图片侵犯了您的版权,请与我们联系,我们将第一时间删除。
 
 
更多>同类资讯
推荐图文
推荐资讯
点击排行
网站首页  |  关于我们  |  联系方式  |  使用说明  |  隐私政策  |  免责声明  |  网站地图  |   |  粤ICP备05102027号

粤公网安备 44040202001358号